A website for friends and family

Author: Joel (Page 3 of 22)

Plants and Plastering

Post by Daphne.

Over the last week a couple of my orders from the forestry services have arrived. The plants arrive small and bareroot, so they are easy to plant. But I have a lot of them. So I asked some friends for help. Louisa helped me with the 7 grey dogwood and the 5 elderberry.

Then today Cathy and Louisa (above) helped me with maybe 10ish red osier dogwood. I forget how many were actually planted. I had 20 delivered to me, but that was way too many for the space. I gave a few to Louisa and I’ll give the rest away to the Arlington Gardeners.

After the planting, I had my typical Wednesday progress report with my architect and builder. The plastering has started on the second floor.

And we had to make a decision about the screening for the heat pump fans. If I just had one fan it wouldn’t be a big deal. But we have a bank with four and they are large and imposing.

I wasn’t really sure I liked our original screening plan. The fans where very visible from the deck. But with an L-shaped screen (above) it blocked the view very well. Now that is not the screen we are using. That is just a mock up to show the location. We will be using 1/4″ black aluminum cut out with abstract flowers. I might end up growing some coral honeysuckle up the front if I can keep it from getting too close to the fans. And keep it from getting too thick. I still need some airflow.

Adding the Blue Board

Right now, inside the house, a crew is putting up blue board on the walls and ceilings. They have finished the second floor and are partway though the first floor. Once the blue board has been installed, they will start plastering.

The crew uses stilts, especially when working on the ceiling installation. Here is a picture of two workers in the living room.

Here are workers in the first floor hallway.

The second floor has all the panels installed. Here is the guest bedroom (2nd floor).

And here is the family room (2nd floor).

In the living room, they have installed wood where the decorative slats will go.

Plastering should start tomorrow or the next day, once all the blue board has been installed.

What a Difference a Day Makes

We went to the house on Thursday to go rowing (more later). Outside they are working on the gutters. In the last post, I showed you a picture of the mounting blocks used for the gutters. Then crew then adds brackets to those blocks as you can see below.

And then the crew mounts the gutter in those brackets as you can see here.

Inside insulation is proceeding at a rapid pace. They appear to be done with the second floor. Here are some progress pictures from the first floor. First the living room wall.

Next the master bedroom ceiling (which is under the roof). The white board is added as an extra layer of insulation since the rafters did not support enough foam.

And here is the ceiling of the kitchen area (which is under the second floor so rockwool is used).

Insulation should be finished tomorrow except for the ceiling of the basement, which will be done later. The builder said that they will start hanging wall board inside the house this Saturday.

Meanwhile, the electricians are continuing to work in the garage wiring up the garage doors.

As far as rowing is concerned, we went out for two and a half hours, following the same path upstream as our last trip. It was quite windy which made the first half challenging as we rowed into the wind, and the second half challenging since the wind made it hard to keep the boat straight as it pushed us downstream.

Now Switching to Rockwool

In my previous posts, I had pictures and talked about how the insulation under the roof and in the exterior walls was closed cell spray foam. Well, they have finished with all that work and now the team is adding rockwool insulation to the interior walls, where we want sound isolation, and under the floors. Here is all the rockwool waiting to be installed (Daphne for scale).

And here is rockwool installed in the wall between the guest bedroom and the family room (second floor).

And here is the backside of that same wall, where you can also see the closed cell spray foam in the exterior wall.

Here is the team installing the rockwool in the front bedroom (second floor).

The basement walls are insulated with a rigid panel product (Thermax), and that work has now finished. The ceiling of the basement will be insulated with rockwool after the rest of the house is done. We decided to leave the walls shiny and not paint them since it reflects light and makes the basement brighter.

On the outside, they have been putting up small pieces of wood product on which the gutters will be mounted. Here is a section from the garage roof.

This week, we discussed the product that will be used for the deck railing, and also the railing in the porch. Here is a sample modeled by our architect. That little wire sticking out halfway down is a sample of the wire that goes between the posts and comprises the majority of the railing.

We also talked about installing screens to hide the condensers that make up the HVAC system. Next week Daphne, the architect and builder will use plywood panels to decide where to put screens.

Things remain on the new schedule for now, but past behavior is no guarantee of future performance.

Current estimated occupancy date: July 31, 2026 (no change).

We Have Garage Doors

These got installed today. Of course, without handles or a remote control, I have no way of going into the garage right now, but I assume that it will get worked out. These look much better than the blue tarps we were using.

I was Pleasantly Mistaken

I thought the garage was supposed to have its wall board installed this coming week, but it actually happened last week. Here are some pictures.

The wall board installation in the house will probably have to wait for the insulation application to be finished.

Trying Out Our New Row Boat

We have bought a row boat and this morning we went for a 2 1/2 hour row, traveling 2.5 miles upstream and then returning.

Here is a picture of the boat at the water’s edge before we launched.

Here are two pictures of Daphne rowing. We actually took turns rowing but I had the camera.

Along the way, we spotted a beaver and I took a picture with my phone. I was pretty far away so the quality is not great.

Finally, on the way home, I took another picture of the back side of the house from the river.

Insulation Underway

They have been installing the insulation all week. It feels to me that they probably just have a few more days of work.

The second floor and under the roof has been finished. Here is a picture from the second floor family room.

The first floor is part done. Here is a picture from the dining room wall.

In the basement, they insulated near the floor. Then they started installing the wall board that will insulate the basement.

This week they will start installing wall board, starting in the garage.

Mid-Week Update in Pictures

Inside the house they are blowing in the insulation. I can not go into the house while they are doing this, but I have this picture of the hose running in the front door and up to the second floor.

Outside the house they are getting ready to install the gutters. Here is a pile of gutters on the deck waiting to be installed.

And today we had a new row boat delivered. Since the boat cover needs to be shipped separately, the boat has been parked under the porch for now. This weekend we will try it out on the river.

House Picture plus Status

We went for a hike on the Fairhaven Trail today and when we were across the river from our house, I took this picture. The siding is done, but the basement still needs stucco, the porch needs screens, the deck needs a railing, and we need to remove all those stickers and protective films.

Inside the house, they have finished insulating the garage and have started insulating in the guest bedroom on the second floor.

Also, because I did not post a picture of this yet, here is the front door. The have sided and trimmed the overhang, but nothing else. The door itself (what is shown is not the real front door), was delivered with a bent frame so it was sent back for repair or replacement. The posts are temporary. The real posts will be added once the stoop is added. The stoop is being cut at a quarry in Vermont and may arrive in a few weeks.

« Older posts Newer posts »

© 2026 Gould Home

Theme by Anders NorenUp ↑