The builder sent me an email with some updates. All of these were expected except the shower ceiling, which was uncertain whether it could get done in time.
- Today the Venetian plastering shower ceiling [was done].
- Hardwood floors installation complete today with sealer coat applied.
- Saturday 2 coats of finish. A final coat at completion of all second [floor] tasks.
- Monday backsplashes installed.
- Monday Primary shower door installed with right hardware along with shelves.
- Tuesday start installation of vinyl floor. Should take 3 days to complete.
- Driveway binder coat hopefully next week.
- Stamski [surveyors / civil engineers] final as-built [inspection] to be done.