This is what is left to do with expected dates, based on the latest meeting with the builder.
- Finish plumbing installation – 7/30, 7/31, 8/1, 8/3
- HVAC system balancing – 7/30, 7/31
- First floor LVT (flooring) installation – 7/31, 8/1, 8/2
- Window cleaning – 8/1
- Game room cabinets – week of 8/3
- Finish alarm and safety systems – 8/3, 8/4
- Appliances delivered and installed – 8/4
- Finish internet, entertainment, telephone – 8/6, 8/7
- Garage epoxy floor installation – 8/6, 8/7
- House cleaners – 8/8, 8/9
- Porch screens installed – week of 8/10
- Driveway paving – t.b.d. (depends on weather)
- Moving van arrives at house – 8/11
- Couches get delivered – 8/12
- Furniture from Cherrystones get delivered – 8/15
Here are some other things, which I do not have a date for, but need to be done.
- HERS testing
- Final coat of sealant on the second floor
- Adding the finish (3 coats) to the basement stairs
- Cutting and installing the master bathroom mirror
- Mounting the pull-up bar in the family room
- Final electrical work, including labeling the circuit breakers
- Mounting the computer monitor arms in the living room (probably done after we move in)
Current estimated occupancy permit date: August 4, 2026.