We did not meet this week. The architect is on vacation and the ceiling of the game room is being sprayed again, so going in the house is off limit for a few days. However, the builder did send me a schedule update.

  • Week of May 18:
    • Install screen panels around HVAC units (maybe)
    • Finish installing and spraying the game room beams
    • Start bathroom tile installation
  • Week of May 25:
    • Finish the deck, including the railing
    • Plaster the game room walls and ceiling
    • Start installing the kitchen, pantry and bathroom cabinets
  • Week of June 1:
    • Lightning protection system installation
    • Install the front stoop (this was delayed a few weeks)
  • Week of June 8:
    • Finish up site (landscaping) work

Things remain on the this schedule for now, but past behavior is no guarantee of future performance. Also, in the estimated occupancy date, I added the word “permit” since it will take us a week (or two) to actually move into the house once we get that permit.

Current estimated occupancy permit date: July 31, 2026 (no change).