We did not meet this week. The architect is on vacation and the ceiling of the game room is being sprayed again, so going in the house is off limit for a few days. However, the builder did send me a schedule update.
- Week of May 18:
- Install screen panels around HVAC units (maybe)
- Finish installing and spraying the game room beams
- Start bathroom tile installation
- Week of May 25:
- Finish the deck, including the railing
- Plaster the game room walls and ceiling
- Start installing the kitchen, pantry and bathroom cabinets
- Week of June 1:
- Lightning protection system installation
- Install the front stoop (this was delayed a few weeks)
- Week of June 8:
- Finish up site (landscaping) work
Things remain on the this schedule for now, but past behavior is no guarantee of future performance. Also, in the estimated occupancy date, I added the word “permit” since it will take us a week (or two) to actually move into the house once we get that permit.
Current estimated occupancy permit date: July 31, 2026 (no change).