I have an update on the schedule from the builder. This all assume that the electrician can find the electrical problem and we can start insulation next week.
- Mar 24 – start insulation
- Apr 6 – start hanging plaster board
- Apr 27 – complete plastering
- May 4 – prime coat all walls and ceilings
After that we have the following tasks for May, June and July:
- Install all trim/cabinets/tile/stone
- Finish electrical and plumbing/flooring/appliances
- Finish painting
There is more work to do outside, including the deck, deck railing, gutters, front stoop, leveling the ground and paving the driveway. But those tasks are not on the critical path for the completion date.
New estimated occupancy date: July 31, 2026.