Update from the builder.
- Plastering (walls and ceilings) on the second floor is finished.
- Plastering on the first floor will be done the week of Apr 20, completed by end of week or sooner.
- Plaster will be left to dry during the week of Apr 27.
- The painter will apply prime coat to interior walls and ceilings during week of May 4.
- Also on May 4, the front stoop gets delivered (which will allow the construction crew to install the front posts.
More updates from the architect.
- Retractable awning will be installed on Apr 21
- Decking will be delivered Apr 23.
- Interior doors will be delivered on Apr 27.
- Front door installation will be done on May 4.
- Kitchen cabinets will be delivered on May 11.