Here is the weekly view of the river. The water is dropping. The mud is not turning green yet.

Here are two progress pictures. The first is from the Southeast corner showing the game room. This is the part of the house that still need the most work on sheathing.

Here is the Northeast corner showing the dining room and kitchen. You can see that on this side of the house, the sheathing is almost done.

The builder is on vacation this week but the subcontractors are still busy working away at finishing the framing. Lots of activity in the house, which you will probably not see on the construction camera. I will move the construction camera inside in a few weeks, but first we will watch the garage foundation work starting next week.

The architect met with the roofing contractor to work out the final details. Should be no issues. I also got to look at the bathroom and kitchen faucets we selected. While they look good, I am worried that the faucets have too much plastic internally and they will break after a few years. Not sure any other brands are any better. They do not make things the way they used to.

Here is a link to the kitchen faucet. And here is a picture showing the plastic internal parts that I know will break.

Total Views: 145