Another snow storm is predicted, so I went to the house to see recent work before the storm. There is still plenty of snow from the last two storms as you can see in the picture of the river view.

As expected, electrical work continues inside. They have finished wiring the second floor subpanel as you can see below.

In the main utility room, they are organizing the wires getting ready to populate the two subpanels.

Elsewhere in the house, the construction crew has installed the real front door. The outside is blocked with a piece of plywood to protect the door, but you can see the inside here.

In the game room, they have start to mock up the (fake) exposed beams. You can see their work near the ceiling in this picture.

The construction camera has been running on the south side of the house, but there is not enough action yet for a new movie. Perhaps, once they get the missing siding hardware and start siding the porch.
Well that’s all for this update. I am not sure how the storm will impact work on Monday, but we will find out soon.