Although we visited the house over the weekend, we did no more landscaping work. Also, there has not been a lot of visible progress in the house since my last update.
Most of the work lately has been installing more electrical plus and switch boxes. We will be reviewing all the locations next Wednesday in what may be a long session.
Meanwhile, the HVAC installation team is mostly done. I did notice that they have finally put the second floor air handling unit in the small attic space above the front bedroom. Here is a picture of the air handling unit, although it has not been connected to the ducts yet.

Last weeks construction camera was mostly boring. I did capture part of a day of siding installation, which I have edited in the following video.
Finally, the water level in the river is up a little from last week because of recent rain. You can see that the inlet in our wetlands (which our neighbor calls “Mary’s Ditch”), now has some water in it closer to the house.

Right now we are trying to engage a botanist who will write a required report to the Natural Resource Commission that will attest that we did, in fact, plant 4 trees and that they are still alive (if the botanist can tell now that the leaves have fallen).
The missing siding components show up on November 14th, which will allow the crew to make more progress on installing the siding.