Installation of the siding was supposed to start this past Monday. However, in order to start the siding, the construction crew needs to be trained by the Nichiha technical representative, and that person has been tied up and will not be on site until October 17th. So instead of showing you the siding on the house, I will show you this picture of what the siding looks like (sitting in the garage).

We had another meeting where we moved around the HVAC units in the utility room. But I think we have a workable plan. Meanwhile, the HVAC team has been busy working on the ducts. The construction camera, unfortunately, was outside (where I wanted to get a video of the siding in progress), so I missed the action from the first half of the week, but I have moved it back into the basement until next Wednesday.
Here are two pictures of the HVAC work. The first shows the air handling units and the second shows more duct work.