They are working on the roof trim, putting in the soffits. Here is a picture of the front of the house. Those soffits (bottom of the roof overhang) will be painted black at some point.

The builder is confident that we are on schedule to be able to move in summer 2026. Meanwhile, here is the short term schedule:
- Roof trim complete – July 11
- Roofing will be done the week of July 14
- Windows will be installed the weeks of July 14 and July 21
- Garage foundation will be dug on June 30
- Garage footing and foundation will be poured the weeks of July 7 and July 14
- The basement slab will be poured the week of August 4
They are about to start on the porch, although they are short a few pieces of wood so finishing the porch will be delayed a little.
We (Daphne and I) need to finish the electrical plan (where all the plugs, switches, lights and Ethernet ports go) by July 14th. Then they will put up place holders in the house for our inspection. Today we picked locations for the outside plugs. Hopefully, I will be able to get an electric (plug-in, not battery) snowblower at some point.
Inside the house, the framing for all the interior walls are in place on the second floor, but not on the first floor yet. Hopefully soon, although I do not have a schedule for that.