So there has been a bunch of activity since my last post. The oil tank has been removed from the basement (although we are still waiting for fire department inspection). Then the silt barrier was installed. Here is a photograph of a section of that barrier.

This morning I had to go to the Registry of Deeds to get the latest Natural Resource Commission Order of Conditions filed. Here is the proof that it has been filed, which I had to show to the NRC today.

Now for the bad news. I screwed up getting the construction camera started and did not get any movies from this week. Oh well. I will work on studying the controls and try to get it working for the next step.
Speaking of the next steps. Before we do anything else, we need to have a NRC site visit. Hopefully, the builder gets that scheduled for next week. Once that is done, we can do the tree and brush removal. We can also get the asbestos in the house removed (although I think that the asbestos removal is not contingent on the NRC site inspection).
Now that the Orders of Conditions (amended) has been registered, nothing is preventing us from filing for our building permit. Currently that is planned for February 18th (it was going to be February 17th, but that is a holiday).